Friday, December 16, 2011

Texas Parks No. 2

Another week of travel for Texas Parks & Wildlife, resulting in a site visit at Lake Casa Blanca where the contractor is continuing work on two Comfort Stations and completing work on the Restroom Facility. Project completion is anticipated to be third week of January 2012. Also, the final walk-through occurred at Chaparral Wildlife Management Area where the ADA inspection passed with flying colors; several items remain on the punch list for completion, however. TPWD will be issuing a Certificate of Substantial Completion as of noon, December 15, 2011. Last, but not least, a Substantial Completion Inspection was held today, December 16, 2011 at Goose Island Bayshore Shelters, and punch list items will be forwarded to the contractor. TPWD will also be issuing a Certificate of Substantial Completion for this project. A final inspection with the Registered Accessibility Specialist will be scheduled for some time in the first week of January, 2012.